A painting scope of work has one job: make three bids comparable, and leave nothing for anyone to discover later.
Most of the change orders we see on builds trace back to the same root cause. The scope said “paint per plan,” three painters each made a different reasonable assumption about what that meant, and the cheapest bid was cheapest because it assumed the least.
Here is what a scope needs to say. It is not long. It is just specific.
The Twelve Lines
1. Which phases are included. Paint touches a build three times: texture and prime after drywall, finish coats after trim and before flooring, and punch at the end. State which of the three the bid covers. This single line prevents more disputes than any other, because a bid excluding punch will always beat one including it.
2. Texture spec, by name. Orange peel, knockdown, smooth, level of drywall finish. “Match existing” is not a spec on a new build. If you want level 5, say level 5, and understand it is substantially more drywall finishing before the painter arrives.
3. Coat counts, per surface type. Walls, ceilings, trim, doors, closets, garage. Two finish coats on walls is standard. Garages and closets are where scopes quietly go to one coat, and where bids diverge.
4. Priming: spot or full. “Spot priming bare wood” and “full prime coat” are different amounts of work and money. On new drywall a full spray prime is standard, and it is also diagnostic, because primer reveals every drywall defect while they are still cheap to fix.
5. Products by manufacturer and line. Not “premium paint.” Sherwin-Williams or Benjamin Moore, and the specific product per surface. A waterborne alkyd enamel on trim behaves nothing like a wall paint, and the price difference is real.
6. The finish schedule. Colours and sheens by room and surface. If it is not finalised at bid time, say so and state who supplies it and by when, because a painter waiting on colours is a painter not holding your schedule.
7. Trim and door treatment. Sprayed before flooring, or brushed after? Sprayed-before is faster, cleaner and cheaper, and it is only possible if the sequence allows it. Make the sequence explicit rather than assuming.
8. Exterior scope and cut edges. Siding, trim, fascia, soffit, garage doors, railings. And a line requiring every field-cut edge to be primed, including the cuts the siding installer makes on site. That is where new construction exteriors most often fail early, and it is invisible at walkthrough.
9. Dependencies. Carpentry complete, HVAC operational, lighting roughed in. Put them in the scope so the conversation about a slipped drywall date is about the schedule, not about blame.
10. Protection and cleanup. Who masks what, who protects finished floors in the punch phase, daily cleanup standard, and who removes debris.
11. Punch process. Number of walkthroughs included, who attends, what response time looks like, and what counts as trade damage versus painter defect. The last one matters: on a build, other trades will damage finished walls, and whether repairing that is included or billable should be decided before it happens rather than after.
12. Closeout documents. A colour and product schedule by room and surface for the homeowner packet, plus leftover paint labelled. Your warranty department will need this in year two, and reconstructing it later is guesswork.
Three Questions That Separate Real Bids
Beyond the document, three questions tell you a lot about who you are dealing with.
What percentage of your hours is prep? Under 30 percent on a repaint means corners. On new construction the ratio differs, but a bidder who cannot answer specifically has not built the job up from takeoff.
What happens if you find rot or damage? The right answer is that they show you, quantify it, and quote it separately before proceeding. A bid that implies nothing will ever be found is either padded or heading for a change order.
How do you prevent texture drift across units? On multi-family this is the question. A good answer involves documented settings, a sample board and consistent operators. A shrug means your buyers will spot the difference between units on tour day.
Why the Cheapest Bid Is Usually a Different Job
The variables a painter can quietly trim are all invisible in a lump sum: prep hours, product grade, coat count, primer coverage, protection, and whether punch is really included.
Two bids on the same 2,400 square foot build can sit $4,000 apart and both be honest quotes, for genuinely different work. Only one of them produces a wall that still looks right at the one-year warranty walk.
This is the same logic that governs repaints, covered in our guide to surface prep. On a build the stakes are higher only because the defects surface after closing, when they are someone’s warranty claim.
Licensing and Insurance, Once
Verify Washington contractor registration yourself at the L&I lookup rather than taking it on faith. There is no dollar threshold exempting small jobs. Every contractor performing construction work in this state must be registered. Ours is PAINTGL885C9.
Then read the certificate rather than the phrase. Washington’s statutory minimum general liability is $250,000 combined single limit, which is the floor for legal registration and nowhere near adequate for a multi-unit build. Ask for $1 million minimum, and confirm workers’ compensation separately. We carry $2 million.
Our guide to hiring a painting contractor covers the verification steps in more detail.
Using This
Lift the twelve lines into your standard bid package and send the same document to every painter. You will get bids you can compare line against line instead of three lump sums you have to reverse-engineer.